Ensuring New Depths at Burgas Port – Phase I
„Capital dredging to ensure access to the newly constructed infrastructure at berths No. 20A and No. 20B, port terminal „Burgas East 2“, stage I“
Co-funded under Priority 3 „Improving intermodality, innovations, modernized traffic management systems, improving transport security and safety“ of the Transport Connectivity Programme 2021-2027
Administrative contract № DPTC–10 от 18.09.2025
Project total cost: 33 962 991,66 €
Total eligible costs: 25 468 815,53 €
Grant: 15 338 756,44 €
European Regional Development Fund: 13 037 942,98 €
National funding: 2 300 813,47 €
Co-financing by the beneficiary: 18 624 235,22 €
Project start: September 2025
Project end: May 2027
Beneficiary: Bulgarian Ports Infrastructure Company
The need for the
implementation of the project arises from the obligations assigned to the
Bulgarian Ports Infrastructure Company under the Maritime Space, Inland
Waterways and Ports of the Republic of Bulgaria Act (MSIWPRBA), to maintain
existing and build new approach channels, port waters, sea and river dredging
disposal sites, breakwaters, protective facilities, networks, and facilities of
the general technical infrastructure, including access infrastructure, in the
ports referred to in Article 106a and in the ports for public transport owned
by the state.
The project
involves the modernization and expansion of the technical infrastructure
(berths No. 20A and No. 20B) for the handling of imports of liquefied petroleum
gas (LPG) and petroleum products at the Port Terminal
Burgas East 2, part of the Port of Burgas, with a view to ensuring the energy
independence of the Republic of Bulgaria through diversification of sources of
supply of petroleum products.
The deepening of
the eastern basin of the Port Terminal Burgas East 2 is a major dredging
project that will allow the design depth of -12.55 m EVRS to be reached. This
will ensure safe access and efficient operation of the port, creating the
necessary conditions for the reception and servicing of larger vessels.
Main Objective: The main
objective of the project is to provide access to the newly constructed
infrastructure of berths No. 20A and No. 20B at the Port Terminal Burgas East 2
by achieving certain design parameters at a depth of not less than -12.55 m
EVRS.
Expected result: Achieved design
parameters for the operational water area and the approach and maneuvering
zones for the maximum design vessels for berths No. 20A and No. 20B at the Port
Terminal Burgas East 2.